Executive Summary Below is the basic concept of TorcSill’s approach to transformer containment and foundation support: During this project there were 2 Siemens (285k lbs
TorcSill provided helical pile foundation solutions throughout the gas plant, including pipe racks, pipe supports and a wide variety of horizontal and vertical process equipment. Steel-to-steel design for all the foundations were critical in improving schedule, reducing construction complexities and reducing owner’s cost to complete.
TorcSill was selected to provide a foundation solution for a pipeline river exposure in the Mid-Continent. With limited time for a planned outage, TorcSill’s engineered solution was designed, manufactured and installed within two weeks of award of the Project.